What installation scenarios are supported by the hydraulic wall panel installer? Are there specific site requirements?

The hydraulic wall panel installer is highly adaptable to various sites. To ensure operational efficiency and construction safety, we recommend that your installation site meets the following conditions:

1. Ground Conditions (Basic Requirements)

Flatness and CleanlinessThe ground should be relatively flat and free of debris. Standard hardened concrete floors are sufficient; if there are slight undulations, the equipment's built-inOutriggers enable ±10° horizontal fine-tuning., adapting to construction sites with a slope of≤15°without requiring additional leveling work.

2. Space and Access Requirements (Site Entry Determination)

Working Height Clearance: Ensure sufficient vertical working space based on panel length. Standard models support wall panels 3–6 meters high; high-spec models enable splicing for heights exceeding 10 meters.

Passage/Doorway Width: This is a required step before model selection.During site surveys, measure construction passage widths and floor height clearances. For narrow spaces such as corridors and doorways,The minimum passage width for Mini compact equipment can be as low as 750 mm.(approx. 0.75 meters); if using standard models, confirm in advance whether the passage width meets the requirements for equipment rotation and clearance. When entering via elevator, verify the elevator car'swidth, depth, and load capacity.

3. Slope and Terrain Adaptation

Indoor Hardened Flooring: Standard models are sufficient, typically offering climbing capabilities of around15° (approx. 10% slope).

Outdoor: Muddy, Potholed, or Soft Ground: Standard wheeled chassis are not recommended.Choose anoff-road heavy-duty chassis(deep-tread tires, high ground clearance) or atracked chassisto improve grip and prevent getting stuck.

4. Power Supply Conditions (No Requirements)

The equipment uses abattery-powered self-propelled systemandDoes not require an external AC power supply.(External AC power customization is available upon request.) Fully charged, it enables continuous operation of8–10 hours, reducing the constraints of temporary site wiring and cable safety hazards.

5. Work Environment and Safety

A safety warning zoneEstablish in the work area; prohibit non-operators from entering the equipment's rotation and lifting zones. Keep equipment clear of trenches, unfilled holes, and other hazardous areas.insufficient bearing capacity.

For splicing operations involvingwall panels exceeding 10 meters in heightoroverweight panelsConduct targeted risk assessments in advance and develop a safety plan for equipment movement paths and the work environment.

Summary: As long as theThe ground has basic flatness.and thePassage width meets equipment requirements., our machine can access the site for operation. If you have concerns about site conditions (such as soft ground, extremely narrow passages, or limited elevator dimensions),Please send us site photos or dimensional data.Our engineers will determine if an off-road chassis, Mini compact model, or custom solution is needed.